Cost-Benefit Analysis of Monitoring-Based Commissioning

Article Tools

A new report titled “Monitoring-Based Commissioning: Benchmarking Analysis of 24 UC/CSU/IOU Projects” is available.

Authored by Evan Mills, PhD, and Paul Mathew, PhD, of Lawrence Berkeley National Laboratory and sponsored by the buildings- and industrial-sector units of the California Energy Commission's Public Interest Energy Research (PIER) program, the report documents an in-depth benchmarking analysis of energy savings from a portfolio of 24 monitoring-based-commissioning (MBCx) projects designed to achieve energy and peak power savings in University of California and California State University buildings.

During the course of the analysis, the authors developed a quality-control/quality-assurance process for gathering and evaluating raw data from project sites and then selected a number of metrics to use for project benchmarking and evaluation, including appropriate normalizations for weather and climate, accounting for variations in central-plant performance, and consideration of differences in building types. The authors performed a cost-benefit analysis of the resulting data set and provided comparisons to projects from a larger commissioning “meta-analysis” database.

The authors identified 1,120 deficiency-intervention combinations. The most common location of deficiencies was HVAC equipment (65 percent of sites), followed by air-handling and distributions systems (59 percent), cooling plants (29 percent), heating plants (24 percent), and terminal units (24 percent). From those interventions flowed significant and highly cost-effective energy savings. For the MBCx cohort, source energy savings of 22 kBtu per square foot per year (10 percent) were achieved, with a range of 2 percent to 25 percent. Median electricity savings were 1.9 kwh per square foot per year (9 percent), with a range of 1 percent to 17 percent. Peak electrical-demand savings were 0.2 w per square foot per year (4 percent), with a range of 3 percent to 11 percent. The aggregate commissioning cost for the 24 projects was $2.9 million.

The authors observed a range of normalized costs from 37 cents per square foot to $1.62 per square foot, with a median value of $1 per square foot for buildings that implemented MBCx projects. Half of the projects were in buildings containing complex and energy-intensive laboratory space, with higher associated costs. A median simple payback of 2.5 years was achieved for the portfolio.

The greatest absolute energy savings and shortest payback times were achieved in laboratory-type facilities. While impacts varied from project to project, on a portfolio basis, the authors found MBCx to be a highly cost-effective means of obtaining significant program-level energy savings across a variety of building types. Energy savings are expected to be more robust and persistent for MBCx projects than for conventionally commissioned ones.

The report can be downloaded at http://cx.lbl.gov/MBCx.html.


Acceptable Use Policy
blog comments powered by Disqus

Marketplace

Recent Comments

Powered by Disqus

Back to Top

Browse Back Issues

August 2010

July 2010

June 2010

May 2010

April 2010

March 2010